A New UNIDROIT–FIDIC Initiative: Why Contractual Stages Still Matter
On 26–28 October 2026, UNIDROIT and FIDIC held the first meeting of their joint Working Group in Rome to develop international principles for construction and engineering contracts.
The initiative aims to improve legal certainty in international projects, where different legal systems and contractual practices may create difficulties.
This development brings attention to a practical contractual question.
Imagine an international construction project. The contractor announces that the works are completed. However, the purchaser has not yet taken possession, and the final performance tests are still pending.
Has the contractor fulfilled its obligations? Who bears the risk if damage occurs at this stage?
These questions are not new.
In its *Legal Guide on Drawing Up International Contracts for the Construction of Industrial Works* (1988), UNCITRAL distinguishes three related but separate stages:
1. Completion: The contractor completes the construction works, potentially demonstrated through completion tests.
2. Take-over:The purchaser takes physical possession of the works.
3. Acceptance:The purchaser confirms satisfaction with the works or agrees to accept them despite certain defects.
The distinction matters because these stages may have different consequences for risk allocation, payments and contractual remedies.
For example, the beginning of three contractual clauses could be drafted as follows:
Completion:
“The Works shall be considered completed upon successful completion of the tests specified in the Contract…”
Take-over:
“The Purchaser shall take physical possession of the Works within the period specified in the Contract…”
Acceptance:
“Following successful performance tests, the Purchaser shall issue a written statement confirming acceptance of the Works…”
These are illustrative examples, not official model clauses.
The UNCITRAL Guide emphasizes the importance of clearly defining the timing and legal consequences of these stages.
The new UNIDROIT–FIDIC initiative is still under development. Although it is a separate project, it reflects the continuing need for greater clarity and predictability in international construction contracts.
References:
1. UNCITRAL, *Legal Guide on Drawing Up International Contracts for the Construction of Industrial Works* (1988), Chapter XIII.
https://uncitral.un.org/sites/default/files/media-documents/uncitral/en/legal_guide_e.pdf
2. FIDIC, *UNIDROIT–FIDIC Working Group Holds First Session in Rome* (9 November 2026).
https://fidic.org/node/47288
#UNIDROIT #FIDIC #UNCITRAL #InternationalContracts #ConstructionLaw